Wednesday 17 February 2016

Windows, door frames, fascias, guttering and plumbing

A lot of progress since last Saturday

Saturday 13/02: surprised to see the chippies onsite.  They installed most of the aluminium window frames, as well as the external door frames and some temp doors

Monday 15/02: Fascia boards and gutters laid out in preparation for installation.

Tuesday 16/02: Fascia boards and gutters installed.  Temporary down-pipes installed.  Plumbing started for hot and cold water.  Most of the pipework is in place.  Flashing for windows is also present.  Roof safety guard rails have been installed.

Wednesday 17/02: Top hats installed in preparation for the colorbond installation.  Plumbing for the solar hot water panel has been run.  Range hood ducting has been installed.

Have asked the site supervisor to check the position of the plumbing for the solar panels.  It looks a little off.  The panel's position was a late alteration & wondering if the change made it to the plumber.

Insulation and colorbond is onsite.  Hopefully the weather is OK tomorrow / Friday so they can be installed