The site supervisor called on Friday. Window alteration not possible as there is 5 week lead time on them & they are due onsite next week. He has advised we can get a film installed post build that will do the job (& other clients have been very happy with). Happy with the solution
Forward schedule for the next couple of weeks includes
- finish roof structure
- fascia and gutters
- roof insulation blanket and colorbond installed
- HWS solar panel installation
- Windows
- Start brick laying
Had a look at the site this morning. The electrician has run the 3 phase from the house to the electrical pit. Now just need the power company to install the meter and make the connection in the pit.