Sunday 31 January 2016

Power, crushed rock & met the framer

The weather has been fantastic for concrete curing; mild and a bit of rain each day

Another site clean was performed on Friday.  They spread the soil around the slab & poured some crushed rock in front of the garage.



Tackled the power issue yesterday (Saturday).  After about 7hrs effort finally managed to create a tunnel from our property to the electrical pit outside.  The clay was a mother.  In hindsight it would have been easier to lift a section of sidewalk, dig & then replace it (& deal with any fallout from the council later).  Sparky can now run the conduit and connect the 3 phase.

Just as I was packing up, the framer arrived and introduced himself.  He then started marking out frame position on the slab so he can hit the ground running on Monday.

The site supervisor has indicated frame should be done this week, roof trusses the following & he has tentatively booked in the brickie for 22 Feb