Wednesday, 25 May 2016

Getting close to handover

Our site supervisor opened the house for us today so our flooring guys could measure up and the solar PV installer could have a look

Lots of progress.  Electrical and plumbing fit-offs done

What's left to complete

  • Painting touch-ups, glazed door painting + final wall coat in the garage
  • Tile grouting (tile left off for bath installs)
  • Shower screens
  • Robes
  • Lock replacement on sliding doors
  • Door hardware
  • Hydronic heating panel installation + boiler and pump
  • External aircon unit, duct vents and air return vent
  • Hot water storage tank and gas booster
  • Ceiling cavity insulation
  • Building clean
  • Garage Doors
  • Appliance installation including range hood (post handover)
Expecting handover in three or so weeks (depending on any defects during final walk-through)



Tuesday, 10 May 2016

Thursday, 5 May 2016

Countdown is on ...

Internal fit out is well underway and the countdown is on with approx 8 to 10 weeks left ...


  • Cabinets have been installed in kitchen, bathrooms and laundry


  • Internal and external painting started


  • Caesarstone benchtops installed


No pictures for this phase as the house is locked up tight.