Sunday 10 April 2016

Eaves installed and waterproofing in bathrooms done




Brickwork has been cleaned, wet area waterproofing completed.  Internal fixings (doors, architraves) underway.  Sliding alfresco doors are now double glazed










Sunday 3 April 2016

Electrical rough-in completed, plaster hung & stopped

It's been a busy week and a bit

Brickwork completed

Electrical
  • Speaker and HDMI cables run
  • Power and lighting rough-in completed
  • Cat 6 and coax rough-in completed

Plaster
  • All plaster was hung in one day and stopped the next
  • Looks like all it needs is another sand, top coat & a final sand