The brickies have been making excellent progress and are expecting to be complete by Wednesday. We're very happy with the brick colour, blending and how well they've been laid.
Alfresco doors have been installed
Moorondah Heating & Cooling has done all the rough in plumbing for the hydronic heating.
Monday, 14 March 2016
Sunday, 6 March 2016
Bricks and Aircon
Busy day on Friday
Wall studs have been planed or packed to ensure they're plumb for plaster installation
Internal cavity sliders were installed yesterday
- Brick laying started on Friday. Very happy
- Aircon duct work completed and related plumbing roughed in for future connection
Wall studs have been planed or packed to ensure they're plumb for plaster installation
Internal cavity sliders were installed yesterday