Monday, 14 March 2016

More bricks, hydronic heating rough-in

The brickies have been making excellent progress and are expecting to be complete by Wednesday.  We're very happy with the brick colour, blending and how well they've been laid.




Alfresco doors have been installed


Moorondah Heating & Cooling has done all the rough in plumbing for the hydronic heating.

Sunday, 6 March 2016

Bricks and Aircon

Busy day on Friday

  • Brick laying started on Friday.  Very happy
  • Aircon duct work completed and related plumbing roughed in for future connection






Wall studs have been planed or packed to ensure they're plumb for plaster installation